Step 5: installing the
concrete blocks

A.

Once the blocks are installed on the edges and along the air supply channel, the blocks are installed in the interior of the slab area

B.

Use insulation to fill in spaces/gaps around plumbing or electrical conduits

C.

Determine location(s) of any "point-loads" and cut-out and remove insulation and leave out blocks for concrete pour of point-loads.